Project Overview
This scope covers fire sprinkler system design, pipe installation, sprinkler head placement, system testing, and inspection coordination. Applicable to residential and commercial buildings.
Typical Projects Include:
- New construction sprinkler system
- Retrofit sprinkler installation in existing building
- Tenant improvement sprinkler modifications
- System expansion or relocation
- Sprinkler head replacement or upgrade
- Fire pump installation
Scope of Work
Design & Planning
| Task | Description |
|---|---|
| Hydraulic Design | Design the sprinkler system layout, pipe sizing, and head placement based on occupancy and hazard classification. |
| Plan Submission | Submit shop drawings to the fire marshal or authority having jurisdiction for review and approval. |
| Permits | Obtain fire protection permits and coordinate with the general contractor on scheduling. |
Installation
| Task | Description |
|---|---|
| Main & Branch Piping | Install risers, cross mains, and branch lines per approved plans. Support and brace all piping to code. |
| Sprinkler Heads | Install sprinkler heads at specified locations with correct type, temperature rating, and coverage pattern. |
| Valves & Connections | Install control valves, check valves, fire department connections (FDC), and flow switches. |
| Fire Pump | Install fire pump and controller if required by the system design. |
Testing & Closeout
| Task | Description |
|---|---|
| Hydrostatic Test | Pressure test the system at 200 PSI (or per code) for 2 hours. Document results. |
| Flow Test | Conduct a main drain test and inspector's test to verify adequate water flow and alarm activation. |
| Final Inspection | Schedule and pass fire marshal inspection. Deliver as-built drawings and test reports. |
Timeline & Milestones
Typical timeline for a fire sprinkler installation. Adjust based on building size and system complexity.
| Phase | Duration | Description |
|---|---|---|
| Design & Approval | 2-4 weeks | System design, plan submission, and permit approval. |
| Material Procurement | 1-3 weeks | Order pipe, fittings, heads, and valves. |
| Installation | 1-4 weeks | Pipe, heads, and valves installed per approved plans. |
| Testing & Inspection | 1-2 days | Hydrostatic test, flow test, and fire marshal inspection. |
Roles & Responsibilities
Client / General Contractor
- •Provide access and coordinate with other trades
- •Ensure water supply meets system requirements
- •Approve design changes and change orders
- •Process payments per the agreed schedule
Fire Sprinkler Contractor
- •Design the system and submit plans for approval
- •Pull fire protection permits
- •Supply and install all materials
- •Conduct required tests and coordinate inspections
- •Deliver as-built drawings and documentation
Materials & Equipment
Piping
- •Black steel or CPVC sprinkler pipe
- •Fittings (grooved, threaded, or welded)
- •Pipe hangers, braces, and supports
Heads & Valves
- •Sprinkler heads (pendant, upright, or sidewall)
- •Control valves and check valves
- •Flow switches and tamper switches
- •Fire department connection (FDC)
Accessories
- •Escutcheons and cover plates
- •Inspector's test connection
- •Drain piping and signage
Quality Control Standards
NFPA 13/13R/13D Compliance
System designed and installed per the applicable NFPA standard for the building type.
Approved Materials
All pipe, fittings, and heads are UL listed or FM approved for fire protection use.
Hydrostatic Testing
System holds required test pressure with no leaks before acceptance.
Safety Protocols
Fall Protection
Use ladders, lifts, and fall protection when installing overhead piping.
Hot Work Safety
Follow hot work permit procedures when welding or cutting pipe on site.
General Site Safety
Wear PPE. Coordinate with other trades to avoid conflicts in active work areas.
Project Documentation
- Approved shop drawings
- Permit and inspection records
- Hydrostatic test report
- Main drain and flow test results
- As-built drawings
- Material certifications and cut sheets
Financial Terms
Payment Structure
Payments tied to project milestones — deposit at contract signing, progress payments during installation, final payment after inspection approval.
Terms & Conditions
- •Deposit due at contract signing (typically 20-30%)
- •Progress payment at 50% installation completion
- •Final payment due after fire marshal inspection passes
- •Change orders require written approval before work proceeds
- •Payment due within 30 days of invoice
Acceptance Criteria & Sign-Off
The project is considered complete when the following criteria are met:
- 1System installed per approved shop drawings
- 2Hydrostatic test passed with no leaks
- 3Flow test confirms adequate water supply
- 4Fire marshal inspection passed
- 5All documentation delivered to client
- 6Work area cleaned up
Frequently Asked Questions
Ready to Use This Fire Sprinkler Installation Template?
Fill in your project details and download a professional, customized scope of work PDF in seconds.
Related Templates
Plumbing
Plumbing Scope of Work Template
View Template →HVAC
HVAC Scope of Work Template
View Template →Electrical
Electrical Scope of Work Template
View Template →General Contractor
General Contractor Scope of Work Template
View Template →Framing
Framing Scope of Work Template
View Template →Drywall
Drywall Scope of Work Template
View Template →