Project Overview
This scope covers masonry work including CMU block walls, brick veneer, stone installation, mortar work, and related waterproofing. Applicable to residential and commercial projects.
Typical Projects Include:
- CMU block foundation or wall
- Brick veneer installation
- Stone veneer or natural stone
- Fireplace or chimney construction
- Retaining wall (block or stone)
- Masonry repair and repointing
Scope of Work
Prep & Layout
| Task | Description |
|---|---|
| Layout | Lay out wall locations, corners, and openings per plans. Set string lines and verify dimensions. |
| Material Staging | Stage block, brick, or stone and mortar materials in accessible locations near the work area. |
| Scaffolding | Set up scaffolding or staging as needed for walls above working height. |
Masonry Installation
| Task | Description |
|---|---|
| Wall Construction | Lay block, brick, or stone per plans. Maintain plumb, level, and consistent joint width. |
| Reinforcement | Install rebar and grout in block cells as specified. Fill bond beams and lintels. |
| Mortar Joints | Tool joints to specified profile (concave, raked, flush, etc.) for appearance and weather resistance. |
| Flashing & Weep Holes | Install flashing and weep holes at the base of veneer walls and above openings as required. |
Finish & Cleanup
| Task | Description |
|---|---|
| Cleaning | Clean mortar droppings and stains from finished masonry surfaces. |
| Waterproofing | Apply waterproofing or damp-proofing to below-grade masonry as specified. |
| Scaffold Removal | Remove scaffolding and clean up all debris and excess material. |
Timeline & Milestones
Typical timeline for a masonry project. Production depends on wall area and complexity.
| Phase | Duration | Description |
|---|---|---|
| Prep & Staging | 1-2 days | Layout, material delivery, and scaffolding setup. |
| Masonry Installation | 3-15 days | Block, brick, or stone laying. Duration depends on wall area. |
| Finish & Cleanup | 1-3 days | Cleaning, waterproofing, scaffold removal, and site cleanup. |
Roles & Responsibilities
Client / General Contractor
- •Provide a level footing or foundation to build on
- •Confirm dimensions and material selections
- •Coordinate with other trades (framing, waterproofing)
- •Process payments per the agreed schedule
Masonry Contractor
- •Supply all masonry materials and mortar
- •Build walls per plans and specifications
- •Install reinforcement and flashing as required
- •Clean finished surfaces and remove scaffolding
- •Clean up the work area
Materials & Equipment
Masonry Units
- •CMU block (size and type per spec)
- •Brick (type, color, and size per spec)
- •Natural or manufactured stone
- •Lintels and bond beam block
Mortar & Grout
- •Mortar mix (Type S, N, or M as specified)
- •Grout for reinforced cells
- •Mortar color (if specified)
Accessories
- •Rebar and wall ties
- •Flashing and weep hole material
- •Waterproofing or damp-proofing
- •Joint sealant and backer rod
Quality Control Standards
Plumb & Level
All walls built plumb, level, and to correct dimensions.
Consistent Joints
Mortar joints uniform in width and properly tooled throughout.
Code Compliance
Reinforcement, grouting, and wall ties installed per building code.
Safety Protocols
Scaffold Safety
Scaffold erected per OSHA standards with guardrails, toeboards, and proper planking.
Material Handling
Use proper lifting techniques. Block and stone are heavy — use mechanical assists when possible.
Silica Dust
Use wet cutting methods and wear respirators when cutting block, brick, or stone.
Project Documentation
- Signed contract and scope of work
- Material specifications and color samples
- Permit and inspection records
- Photos of reinforcement before grouting
- Waterproofing application records
- Warranty information
Financial Terms
Payment Structure
Payments tied to milestones — deposit at signing, progress payments during installation, final payment after completion.
Terms & Conditions
- •Deposit due at contract signing (typically 20-30%)
- •Progress payments based on percentage of wall completed
- •Final payment due after cleaning and scaffold removal
- •Change orders require written approval
- •Payment due within 30 days of invoice
Acceptance Criteria & Sign-Off
The project is considered complete when the following criteria are met:
- 1Walls built to correct dimensions, plumb, and level
- 2Mortar joints consistent and properly tooled
- 3Reinforcement installed per specs
- 4Flashing and weep holes in place
- 5Surfaces cleaned and free of mortar stains
- 6Work area cleaned up
Frequently Asked Questions
Ready to Use This Masonry Template?
Fill in your project details and download a professional, customized scope of work PDF in seconds.
Related Templates
Concrete
Concrete Scope of Work Template
View Template →Framing
Framing Scope of Work Template
View Template →Waterproofing
Waterproofing Scope of Work Template
View Template →Retaining Wall
Retaining Wall Scope of Work Template
View Template →Foundation Repair
Foundation Repair Scope of Work Template
View Template →Excavation
Excavation Scope of Work Template
View Template →