Project Overview
This scope covers office fit-out work including space planning, demolition, construction of offices and common areas, IT and AV infrastructure, furniture installation, and move-in coordination.
Typical Projects Include:
- Corporate office build-out
- Startup or co-working space fit-out
- Call center or operations floor build-out
- Executive suite renovation
- Open office conversion
- Satellite office setup
Scope of Work
Design & Pre-Construction
| Task | Description |
|---|---|
| Space Planning | Develop the floor plan layout — offices, conference rooms, workstations, break areas, and circulation paths. |
| Design Development | Select finishes, furniture, and fixtures. Develop construction documents for permitting. |
| IT & AV Planning | Plan data cabling, network rooms, AV systems for conference rooms, and power requirements for workstations. |
| Permitting & Procurement | Pull building permits and place orders for long-lead items — furniture, millwork, and specialty fixtures. |
Construction & Installation
| Task | Description |
|---|---|
| Demolition & Prep | Remove existing partitions, ceilings, and finishes. Prep the space for new construction. |
| Walls, Ceilings & MEP | Build new offices and rooms. Install ceiling systems, lighting, HVAC modifications, and electrical. |
| Finishes | Install flooring, paint, wall coverings, glass partitions, and doors throughout the space. |
| IT Infrastructure | Install data cabling, network racks, wireless access points, and AV equipment in conference rooms. |
Furniture & Move-In
| Task | Description |
|---|---|
| Furniture Installation | Receive, assemble, and install all workstations, desks, chairs, and common area furniture. |
| Signage & Branding | Install lobby signage, wayfinding, room numbers, and any branded environmental graphics. |
| Final Cleaning | Deep clean the entire space — windows, floors, surfaces, and restrooms — before move-in. |
| Move-In Coordination | Coordinate the move with the client's team. Manage elevator reservations, loading dock access, and timing. |
Timeline & Milestones
Office fit-out timelines depend on size and complexity. A small office might take 6-8 weeks; a full-floor corporate build-out can take 4-6 months.
| Phase | Duration | Description |
|---|---|---|
| Design & Pre-Construction | 2-6 weeks | Space planning, design, permitting, and procurement of long-lead items. |
| Construction & Installation | 4-16 weeks | Demo, construction, finishes, and IT infrastructure installation. |
| Furniture & Move-In | 1-3 weeks | Furniture install, final cleaning, and coordinated move-in. |
Roles & Responsibilities
Client / Facilities Manager
- •Provide headcount and space requirements
- •Approve design, finishes, and furniture selections
- •Coordinate IT equipment and service provider access
- •Manage the employee move logistics
Fit-Out Contractor
- •Manage construction from demo through furniture install
- •Coordinate all trades, vendors, and building management
- •Deliver the space on schedule and within budget
- •Ensure the space passes all inspections and meets code
- •Provide closeout documentation and warranty information
Materials & Equipment
Construction
- •Metal studs, drywall, and glass partitions
- •Ceiling grid, tiles, and light fixtures
- •Flooring — carpet tile, LVP, or polished concrete
IT & AV
- •CAT6 or CAT6A cabling and patch panels
- •Wireless access points
- •Conference room AV — displays, cameras, speakers
Furniture & Fixtures
- •Workstations and sit-stand desks
- •Task chairs and conference seating
- •Break room and lounge furniture
Quality Control Standards
Design Intent
The finished space matches the approved design — layouts, finishes, and furniture placement.
Functional Systems
All MEP, IT, and AV systems are tested and fully operational before turnover.
Move-In Ready
The space is clean, furnished, and ready for employees to work on day one.
Safety Protocols
Building Coordination
Follow all building construction rules — work hours, freight elevator scheduling, and noise restrictions.
Occupied Building
If the building is occupied, maintain dust barriers, control noise during business hours, and keep common areas clean.
PPE & Housekeeping
Require PPE during construction phases. Keep the work area clean and secure tools and materials daily.
Project Documentation
- Signed contract and scope of work
- Approved floor plans and design documents
- Building permits
- Furniture orders and delivery schedule
- IT and AV specifications
- Punch list
- As-built drawings and closeout package
Financial Terms
Payment Structure
Office fit-outs are typically structured as lump-sum or GMP contracts with progress payments tied to milestones.
Terms & Conditions
- •Deposit due at contract signing (typically 10-20%)
- •Progress payments at major milestones — demo, rough-in, finishes, furniture
- •Furniture deposits required at time of order (typically 50%)
- •Retainage of 5-10% held until punch list completion and move-in
- •Change orders approved in writing before work begins
Acceptance Criteria & Sign-Off
The project is considered complete when the following criteria are met:
- 1Space completed per approved design documents
- 2All systems tested and operational
- 3Furniture installed and configured
- 4Space deep cleaned and move-in ready
- 5All inspections passed
- 6Closeout documents delivered
Frequently Asked Questions
Ready to Use This Office Fit-Out Template?
Fill in your project details and download a professional, customized scope of work PDF in seconds.
Related Templates
Tenant Improvement
Tenant Improvement Scope of Work Template
View Template →General Contractor
General Contractor Scope of Work Template
View Template →Electrical
Electrical Scope of Work Template
View Template →Drywall
Drywall Scope of Work Template
View Template →Flooring
Flooring Scope of Work Template
View Template →Painting
Painting Scope of Work Template
View Template →